Frequently Asked Questions: Exterior Waterproofing and Paint Project

Introduction Link to this section

SFUSD’s commitment to student safety in facilities improvement projects

Student safety is our top priority. We take our responsibility in improving school buildings to support student wellbeing and learning seriously. If construction conditions arise that cannot be safely managed while the school is operating, we will stop or modify the affected work, isolate the area, or take necessary measures before proceeding. SFUSD works closely with highly qualified third-party professionals and experts to ensure that we comply with rigorous safety standards as we complete facilities improvements to benefit student learning and wellbeing.

The FAQ here provides more information and responses to the most frequent questions we received from the Chinese Immersion School De Avila community. We will continue to update this document on a regular basis.  

Data and Test Results Link to this section

In this section, we will post testing locations and results.
  • In this document you will find testing locations and results for August 22, August 30 and September 1.  These testing samples were taken by a third party on the east yard and surrounding areas.

  • As an additional layer of accountability, samples were taken by two different entities and analyzed at two different labs. The first round of tests came back just over the regulatory threshold for indoor areas in the two restrooms next to the yard. The restrooms were then cleaned and retested with results indicating levels under the regulatory threshold. 

Update: Responses to new questions and requests for information from the Community Meeting on September 2
Link to this section

We are including responses to new questions and requests for information following the Sept. 2 Community Meeting and submissions to the online question form. Please note that many people had similar questions, and some questions were already answered in the FAQs posted previously. Please review the FAQs and if you do not see a response to your question, let us know. 

What is the updated project plan for the remainder of this project?

The proposed project restart date is Wednesday, September 16th.  

Once the project resumes, all work will occur after 6pm on weekdays and Saturdays and Sundays or long weekends or breaks.  Work will not happen when students are present.

The paint removal work will take place over the Indigenous Peoples' Day weekend and Thanksgiving Break, with cleaning and testing taking place before students return to school.

Task 1:  Paint removal on the eastern side of the building: 

Work Dates:  

Friday, October 9 at 6pm - Monday, October 12 at 6pm (Indigenous Peoples' Day)

Friday, November 20 at 6pm - Sunday, November 29 at 6pm (Thanksgiving Break)

On Monday, October 12 and Sunday, November 29, cleaning and testing will take place in advance of students returning.

Task 2:  Concrete repairs, sealant repairs and wall painting:

Work Dates:  

Starting Wednesday, September 16, every weekday evening from 6pm - 10pm and weekends from 9am - 5pm.

The work for this task is scheduled to end on Friday, January 15, 2027

The project schedule is amended to allow this work to begin on September 16. Work will happen after 6pm and on weekends. Cleaning and testing is not required for this scope of work.

Task 3: Window replacement: 

Work Dates: Same work schedule as paint removal; the work will happen in tandem.  See above.

Task 4:  School sign add-back: 

Work Dates:  December 26, 2026

Task 5: Scaffolding removal: 

Parts of scaffolding will be removed when painting is completed of sections of the building about 5 days at project completion.

Work Dates (all taking place after 6pm)  Sunday, September 27th, Thursday, December 3rd and Friday, January 15th, 2027
 

As the project resumes, the contractor can provide a detailed two-week look ahead on a weekly basis, with more information on the location of work and schedule. Any updates or changes in schedule will be communicated to the school community.

What else do we need to understand about lead exposure and contamination? What is UCSF’s role in evaluating and supporting safety?

As we have shared in the previous FAQs, lead is a common environmental contaminant and cannot biodegrade. The Environmental Protection Agency states that natural levels of lead in soil range from 50 and 400 parts per million. While we do not know if any level of lead is “safe” for a human, we also know that none of us live in a lead-free environment. The presence of lead or other regulated building materials does not itself make a building unsafe to occupy. These materials are common in older buildings throughout San Francisco and around the country. The concern arises when certain materials are disturbed without appropriate controls—which is exactly what the District's hazardous materials procedures are designed to prevent.  Also see California Department of Health lead FAQ.

We want to add that SFUSD is working in partnership with Dr. Gina Solomon and a team of UCSF doctors and researchers at the Western States Pediatric Environmental Health Specialty Units. They are partnering with the district as an outside reviewer and resource for this project.  

Dr. Solomon and her team reviewed all of SFUSD’s data, and walked the site with SFUSD staff and the independent Industrial Hygienist. They also attended the community meeting on September 2. She and her team shared their website as a resource for families interested in learning more. 

Dr. Solomon and her team acknowledged that lead is bad and we do not want our kids exposed to lead, if at all possible. However, in the modern cities, we will find traces of lead almost everywhere due to historic use of lead in paint and in gasoline. She shared that we cannot realistically expect zero when collecting test samples. The goal is to keep the levels as low as possible, and take steps to prevent it from getting into the kids' bodies.

After reviewing procedures and touring the site, the UCSF team affirmed that the project employs many layers of safeguards. There is still a need for vigilance, and Dr. Solomon and her team will continue to review test results, and work with SFUSD to support finishing this project as quickly as possible without putting kids at risk. 

What is the plan for play yard areas? Will the district test soil in the play yard areas?

The East play yards have been evaluated for the presence of lead dust on multiple occasions, beginning at the onset of the project. The initial assessment of the east side play yard has been by way of visual assessment and monitoring of the work within the fully contained work area over the summer.  During this time, the contractor executed the work in conformance with the project specifications with zero findings of containment breach.  

In August, while the project was on pause, the interior and exterior wipe samples were collected and all results were reported well below regulatory action limits.

Subsequently, at the end of August, the east side play yards were vacuumed using DOP-tested HEPA vacuums and resampled for a second time by two independent parties using two independent different laboratories.  The results from this second round of testing were again well below regulatory action limits with many being below method detection limits. 

Based on several factors, including the means and methods of construction work performed to-date, the training of workers involved in the construction, the engineering controls, observations made during construction and the resulting analytical results, the East Side yards can be accessed for general use.

Based on the findings to date and the comments noted above, no further cleaning of the play yard(s) as it relates to the construction project is scheduled until the work begins again, and is completed.  Once the construction commences, full-time monitoring and observation will be performed.

When the exterior work is complete, the east play yard surfaces will be HEPA vacuumed and re-tested, including soil testing.  

What is the district’s plan for cleaning and environmental testing to keep children safe during the project?

At this time, work has not yet restarted so no cleaning (beyond regular custodial cleaning) nor testing has taken place since August 29 - September 1.

When work restarts on the exterior, there will be full time monitoring and observation to enforce the project specification as it relates to environmental safety, including lead dust.

When the exterior is complete, the east play yard surfaces will be HEPA vacuumed and re-tested, including soil testing.  Until then, there is no extra cleaning planned.

When the interior work on the windows begins, there will be daily air monitoring taking place inside the affected classroom and at the conclusion of the work in a given room; the area will be wipe tested before re-occupancy.

Please also refer to these two questions (District approach to testing) and Safety measures in the FAQs posted from August 25-27 for a more detailed description of cleaning and testing procedures.  

Additional Questions Posted on Friday, Aug. 28 

Will the district do another round of cleaning at the site, and bring in another third-party environmental testing firm?

This weekend, on Saturday and Sunday, August 29-30, the district will bring in a contractor to do a deep, thorough cleaning of the east side yards. They will use a HEPA vacuum to remove any residual dust from these areas. Another industrial hygiene and environmental monitoring firm, ACC Environmental Consultants, will then do sampling and testing after the yard is cleaned, and will share these results with the district and school next week (week of August 31). 

Can the district provide HEPA filters to ensure safe indoor air quality?

35 new Austin brand Portable Air Cleaners (PACs) were delivered to CISDA by August 28. 2026. They are equipped with MERV 18 filters with ultra-efficient hospital-grade particle capture. MERV 18 filters surpass standard HEPA requirements.

If work is to resume after school hours and during holiday/breaks what are the safety measures in place to prevent exposure?

The district adheres to very strict requirements and enforces extensive containment procedures for lead paint removal work. This includes comprehensive cleaning when work concludes, inspected and approved by an independent industrial hygienist. These safety measures are detailed in Question 4 in the FAQs shared with the community on Tuesday August 25, and posted on the school’s website

Will portable handwashing stations be available for students during recess or meal times?

Yes, the district is providing five handwashing stations to place on the yards at CISDA. They are expected to arrive by Tuesday, September 1. The stations include paper towel dispensers. Waste water is contained within the unit, and the stations are serviced once per week. We will communicate this maintenance information to CISDA leadership and staff. Please note that the water at handwashing stations is not safe for drinking, and is for handwashing only. 

Questions Posted from Aug. 25-27

What is this project and why does it need to happen now? What other sites have had similar projects?

The project at Chinese Immersion School De Avila was prioritized because the building walls and windows have been leaking, letting water into the building. To protect the building long-term, the project scope includes removing exterior paint, patching and sealing any damaged areas, replacing windows, and repainting the outside of the building. This is an important investment in the school, and one that needs to happen before winter and the rainy season begins. SFUSD works hard to schedule construction work during school breaks whenever possible, but sometimes it is not possible to complete everything in these limited timeframes. Supply chain delays, contractor availability, weather, school events, and many other factors can all impact the schedule and extend the time it takes to complete a project. This is why some work for the current project at CISDA is extended into the school year.

SFUSD regularly completes major construction projects while schools remain open and occupied. This is a standard part of managing projects to improve our school facilities, and our construction plans and safety protocols are specifically designed to allow students and staff to continue using the campus safely while work is underway. Our project managers are experienced in managing this work at active school sites. SFUSD buildings are schools first, and construction activity is designed to occur around that. We will always prioritize student safety and health as we deliver these upgrades to SFUSD buildings.

What is the project plan for the remainder of this project?

Once the project resumes, all work will occur after 6pm on weekdays and Saturdays and Sundays. Work will not happen when students are present.

  • Paint removal on the eastern side of building: 4 weeks, after 6pm only
    This work requires ongoing containment, mitigation, and cleaning procedures detailed in Question 4.
  • Concrete repairs and sealant repairs: 4-5 weeks, beginning as paint removal is complete in each section
    This work does not require containment, but dust mitigation and window wrapping will continue
  • Window replacement: 2-3 weeks, following completion of concrete and sealant repairs. 
    Window replacement in each classroom will take 3-5 days, including testing and cleaning once complete. It will be phased by classroom, and we will coordinate with school leadership on a schedule for moving classrooms out during work. We will also complete as much work as possible over school breaks.
  • Wall painting: 3 weeks, occurring after window replacement is complete.
  • School sign add-back: about 3 days
  • Scaffolding removal: about 5 days at project completion

As the project resumes, the contractor can provide a detailed two-week look ahead on a weekly basis, with more information on the location of work and schedule. Any updates or changes in schedule will be communicated to the school community.

What is the paint removal process being used, and why is this the best approach?

The district complies with strict standards for lead-related construction activities. It contains all work areas with plastic sheet barriers, which help prevent paint chips, dust and debris from spreading outside of the work area. For this project, the contractor is using a chemical stripper to remove paint. In the industrial hygienist’s opinion, this is the best approach because it is a relatively fast and clean method which does not create dust, and provides a workable surface for the waterproofing that will happen next. After the chemical stripper is applied, surfaces will be power-washed, and this cleaning water will be collected and disposed according to State and federal regulations. This water is temporarily stored and secured in approved drums, and subsequently transported off site for disposal. Similarly, the bulk waste material from the paint removal process is collected as it is generated, stored in secured containers and transported off site for disposal.

What safety measures are in place and how can we trust them? (be specific about containment, testing, air filters, etc - also general safety measures we use as a district)

Below we outline the safety measures we follow for this project:

Before a project begins:

✔ We hire an independent, third-party environmental and industrial hygiene firm to evaluate the site for hazardous materials, and interpret and analyze results. Staff at these firms must be certified at both state and federal levels. Evaluation firms approach each project as its own unique set of conditions; work methods and engineering controls generally exceed the regulatory requirements to ensure safety.  

✔ Once the construction contractor is selected, they prepare a Work Plan to address methods, procedures, regulatory requirements and materials and supplies. The Work Plan is reviewed by the independent, third-party environmental and industrial hygiene firm, and the contractor cannot start work until it is approved.  

✔ Before starting construction, the contractor sets up the site for work. The industrial hygienist inspects the set up and collects baseline data (ie soil sampling). Work can begin after this data and set up are approved.


During a project: 
✔ The consultant reviews the worker sign in sheet (daily) to confirm credentials, etc; Workers enter the outermost designated chamber and put on protective clothing (PPE) before entering the contained work area (this is the “regulated area” where a second type of posted signage exists). They must also follow a strict procedure to remove and dispose of their PPE at the end of their shift, clean and secure their ventilator, wash their hands, and vacuum themselves from head to toe to eliminate any potential contamination. This process is field verified as part of the monitoring task by the 3rd party industrial hygiene consultant.    

✔ As part of the paint removal process, a paste-like compound is applied to the paint using a hudson-style airless sprayer.  Once complete, a layer of poly sheeting is applied to the compound to facilitate breakdown and softening of the paint. This sits for ~24 hrs.  During paint removal, the softened paint is scraped off the substrate and is bagged within the contained area, then bagged again in the changing chamber. It is placed in designated trash drums outside of the work area, and is then disposed of as a regulated waste material and is picked up by a specialized transport crew.

✔ At the end of every work day, workers HEPA vacuum all areas and an independent environmental inspector (hired by MECA) does a visual inspection to check if the work area is properly cleaned.

✔ After all paint is removed, the wall is power washed or cleaned to remove any chemical residues on the surfaces that would negatively impact the new coating required to waterproof walls. The ground/floor is protected and lined to collect residual rinsate, and then this waste water is bagged and disposed of in the same manner as paint scrapings. 

✔ Throughout this phase, the air inside the containment area is filtered using HEPA and charcoal filters on air scrubbers and the vacuums are also HEPA filtered.Each device is tested on-site by an independent 3rd party prior to use. 

After the Project

✔ Once the project is substantially complete, the containment is visually inspected for final clearance.  CDPH Certified Inspector/Risk Assessor performs a visual inspection and soil sampling for exterior construction-based projects, and clearance wipe sampling on interior projects before re-occupancy.

What regulatory agencies does SFUSD comply with and follow? What standards do we use?

SFUSD complies with the relevant requirements of many agencies including:

  • Cal/OSHA (8 CCR 1532.1) - Lead in Construction
  • Title 8, California Code of Regulations (CCR), Section 5198 - Lead in General Industry;, Title 17, California Code of Regulations (CCR), Division 1, Chapter 8 (Sections 35001 – 36100) - Accreditation, Certification, and Work Practices for Lead-Based Paint and Lead Hazards."  
  • Title 40, Code of Federal Regulations (CFR), Part 745, Subpart E (40 CFR § 745.80 – § 745.92) - Environmental Protection Agency's (EPA) Renovation, Repair, and Painting (RRP); 
  • HUD - Child-Occupied Facilities, U.S. Department of Housing and Urban Development (HUD) - Title 24 of the Code of Federal Regulations (CFR), Part 35; 
  • Title 8, California Code of Regulations (CCR), Section 1529  - Asbestos Construction; Title 8, California Code of Regulations (CCR), Section 5208 (8 CCR § 5208) - Lead in General Industry;   
  • BAAQMD Regulation 11, Rule 2 (Rule 11-2): Asbestos Demolition, Renovation and Manufacturing; 
  • Asbestos Hazard Emergency Response Act (AHERA) - Title 40, Code of Federal Regulations (CFR), Part 763, Subpart E (40 CFR § 763.80 – § 763.99); 
  • US EPA: Resource Conservation and Recovery Act (RCRA), Title 40 of the Code of Federal Regulations (CFR), Parts 260 through 279; 
  • CA DTSC Title 22, California Code of Regulations (CCR), Division 4.5 (Specifically: 22 CCR §§ 66260.1 – 67900.12)   

For a more detailed comparison of SFUSD’s regulatory compliance related to lead paint, please see here.

What did the San Francisco Department of Building Inspection find?

An inspector from the San Francisco Department of Building Inspection conducted an investigation of a complaint related to the project and found no violations of the San Francisco Housing Code

What do we need to understand about lead exposure and contamination?

What is the district’s approach to testing for lead or other contaminants in buildings?

The District has obligations for ongoing identification and monitoring of hazardous materials, and also has specific requirements for capital projects like this one. 

As summarized in Question 4, every project undergoes a rigorous testing process to ensure that materials containing regulated levels of hazardous materials are identified, reported and subsequently removed following strict protocols based on requirements outlined in Q5. Reoccupancy is only permitted after each area has been cleared.

Non-construction related programs (ie maintenance and operations) are in-place to monitor the condition of asbestos in school facilities.  The District inspects each facility in accordance with the U.S. Environmental Protection Agency’s Asbestos Hazard Emergency Response Act (EPA-AHERA) program to assure effective management and compliance. 

Capital projects: SFUSD’s Facilities Department maintains a pool of on-call industrial hygienists who can be contacted as needed by the District to perform hazardous materials surveys, write construction specifications, and monitor the general contractor’s adherence to hazmat management requirements. At the outset of a new capital project, SFUSD requests proposals from industrial hygiene consultants in the pool to perform a hazardous materials survey of the District’s area of work. If hazardous materials are identified in this survey, the industrial hygienist writes a list of hazardous materials requirements for the project contractor to adhere to during construction and includes them in the project drawings and contract documents. The bidding contractors sign a certification that they understand and have reviewed these specifications when they sign a construction contract with the District. The industrial hygienist then performs construction monitoring of the contractor’s work throughout the construction period to ensure that the contractor is adhering to the project documents and requirements. At the end of major project phases, when classrooms or other school spaces have been cleaned following construction activity and are turned back over to the school site, the industrial hygienist conducts final visual inspection and subsequent air and/or surface testing in the space to ensure that the space is ready for students to occupy safely. 
 

What requirements does the district comply with to notify families about projects that involve lead abatement?

The work at CISDA is a construction project that required disturbance of various levels of lead. It is not an abatement project. This is notable only because the purpose of this project was not to eradicate a “lead hazard”; rather it required the removal of a paint film from a wall surface in which the paint contained lead. The regulations and requirements concerning lead can be complex; therefore, it is important to understand the distinction between a construction project that has lead that is being disturbed/removed as opposed to a project that its sole intent is to remove a lead hazard (ie “abating a lead hazard”).  The exterior waterproofing project is a construction project and not a lead abatement project. 

How will the district notify families if there is exposure or tests indicate hazardous levels of lead or other contaminants?

If the District’s industrial hygienist determines that any monitoring or containment requirements have not been followed by the contractor, the industrial hygienist is required to immediately notify the District and advise on what measures the contractor needs to take to ensure student safety.  In addition, there are safeguards built into the project specifications to reduce or eliminate the probability of an elevated test result outside of a controlled area. For example, for projects where daily air monitoring outside of the enclosed/contained area is occurring, a Stop Work Order would be issued if the results were ½ of the government permissible limit.  Furthermore, the District will not open spaces to students/faculty or other contractors that are not first inspected and cleared and determined safe to reoccupy. In the event a hazardous environment was observed, SFUSD will notify the school’s Principal immediately, and will develop a communication plan to promptly notify families and staff. 

The District’s industrial hygienist has not advised the District that there are safety concerns with this project’s construction to date, which is why proactive noticing was not distributed to site staff and students. 

Which contractors are working on this project, and what are their qualifications?

SFUSD received eight bids for this project and accepted the lowest responsible and responsive bid, as required by public contracting code. Here are the bid results. Firm details and insurance information can be found in the linked contract documents below.

Waterproofing contractor:  

Urban Waterproofing Inc. is a reputable construction firm specializing in waterproofing projects for more than 20 years. 

Website: https://www.urbanwaterproofing.com 
Contract: Urban Waterproofing Contract

Industrial Hygienist: 

Millennium Consulting Assoc. (MECA) is an environmental engineering, industrial hygiene, and building science firm that has worked for the district for 28+ years.  

Website: Millennium Consulting Associates

MECA Statement of Qualifications

MECA Contracts

Demolition/paint removal contractor: 

Sterling Environmental Inc. is a subcontractor with Urban Waterproofing. Sterling is a firm specializing in hazardous materials services since 1988 and has been involved with numerous SFUSD projects.

Website: www.sterlingenv.com  

Why can’t the project be paused, or why can’t we relocate to another location during this work?

The project is in Phase 1 with approximately 90% of the paint removal complete. The remaining bulk of the work involves waterproofing, window replacement and painting which cannot occur in cold, wet weather. Pausing the current phase of the project means the building is susceptible to further water intrusion, risking damage. The full scope of the project is more extensive than can be completed in a single school break, summer included. 

Specifically, this project has tangible benefits to the short and long term integrity of the building, and these benefits accrue to students and staff. The building currently leaks both through the walls and the existing aluminum windows. Once water gets inside the building envelope, it can quickly damage materials and systems that were never designed to get wet. As we near a forecasted wet winter, completing this work now can help minimize potential water intrusion impacts that could occur if the work is not completed. 

SFUSD is closely monitoring work conditions in collaboration with a team of experts. We are committed to providing a safe and healthy environment for students and staff. The team will actively communicate any changes to the project if health and safety standards have been compromised at the work site.

Relocating a school community is a decision that can have significant impacts on students and families. It affects transportation, instructional programs, student services, staffing, meals, after-school activities, and access to the school community, and it also requires another facility with sufficient capacity and appropriate spaces to accommodate the program. For those reasons, the District’s approach is to keep schools operating in place when construction can be safely managed around them. This project’s construction phasing, containment measures, and hazardous materials protocols are specifically designed to make that possible. A relocation would be considered if our qualified professionals determined that the work could not be safely performed while the campus remains occupied.

What steps are being taken to address ventilation, heat, and lighting concerns for classrooms that do not have window access as a result of the work?

Part of this project includes removing and replacing windows, which does block access and/or limit the ability to open windows. The window masking also prevents dust from entering classrooms. On Monday, August 24, 2026, SFUSD Facilities delivered a Portable Air Cleaners outfit with HEPA filtration to CISDA for use in the classrooms. 18” floor fans are also provided to increase air flow. Students will continue to have opportunities for outdoor learning and play in the yard. We will continue to push to complete this part of the project as efficiently as possible. We will also work with school staff on additional ways to support students in impacted classrooms.  

Will the district test soil in the play yard areas?

SFUSD takes student and staff health seriously. Though it is not a regulatory requirement, staff commissioned soil testing on August 20, 2026. Six samples were collected: two from bare soil east side of the garden area, two from planter boxes, two from bare soil west side. Wipe samples from the play pad (yard 1), short slide (yard 1), yard 2 north area (2), yard 3 play area, and yard 4 @ concrete landing. Lead levels ranged from 8 to 35 mg/kg, below California Department of Public Health’s 400 mg/kg standard for children's play areas, US EPA/HUD and CA Title 17 standards.

What communications and updates about the project can we expect to receive from SFUSD?

We will provide updates on the project every Thursday evening. These updates will be available in Chinese, Spanish, and English. In addition, we will hold an in-person community meeting in the next week to provide project updates and answer outstanding concerns

Can students receive independent study while the project is ongoing if parents do not feel comfortable sending their student to school?

Because the school has been determined to be safe, students are expected to attend school as usual. Absences related to concerns about the work will not be excused. Independent Study is not being offered as an alternative. See also SFUSD website information here.

This page was last updated on September 10, 2026