The modernization of Sheridan Elementary School was completed in 2021. The upgrade included a cafeteria refresh, a serving kitchen renovation, and bathroom improvements. Roofs in the buildings were updated to prevent leaks. HVAC, power, data, and security systems were upgraded to improve the safety and learning environment for students. On the exterior of the building, there was the addition of a green schoolyard and the playground was regraded.
Classroom Renovations
New Outdoor Play Yards
New Green Schoolyard
Project Dashboard Link to this section
Dashboard currently under construction. Coming back online soon!
General Information
Link to this section
Project Details
| Architect: |
Lemanski & Rockwell Architects Inc. |
| General Contractor: | Wickman Development and Construction |
| Construction Manager: | Vanir Construction Management, Inc. |
| Bid Amount (Hard Cost): | $12,123,843 |
| Change Order Amount: | $2,085,244.31 (17.20% of bid amount) |
| Final Contract Amount: | $14,209,087.31 |
Project Description
Scope of work including but not limited to:
- Voluntary seismic upgrades and associated finishes removal and replacement at south wing only.
- Site accessibility upgrades
- Playground regrading and landscape improvements
- Green schoolyard addition
- Reroofing at multi-purpose building
- Replacement of glazed roof with standing seam metal roof and ventilation cupola at main entry.
- Serving kitchen renovation
- Cafeteria refresh
- Toilet room upgrades - new fixtures, partitions, and flooring
- Programmatic improvements including new pre-k restrooms and replanned administrative offices
- HVAC and controls upgrades
- Power, data, and security system upgrades
- Replacement of interior and exterior lighting
- Elevator controls upgrades
- Exterior and interior painting
- Classroom casework replacement at multi-purpose building
- Replacement of room identification and directional signage