General Information
Architect: | CAW Architects, Inc. |
General Contractor: | Arntz Builders, Inc. |
Construction Manager: | AECOM |
Bid Amount (Hard Cost): | $12,394,278 |
Project Description
Complete rehabilitation to existing 2-story annex building and renovation of administration building including:
- Replacement of all windows; complete renovation of classrooms and administrative offices
- Reconstruction of damaged wood structure, foundation and structural upgrades
- New lighting; new fire alarm system
- Complete renovation of all toilet facilities
- Site work including addition of pergola